INQUIRY FORM




L I V Developers has announced the completion of the raft casting.

September 30, 2017
L I V Developers has announced the completion of the raft casting at its LIV Residence Dubai Marina project. Valued at more than AED 400 million, the iconic tower development is scheduled for handover in Q2 2019. The tower will offer 27 floors with a mix of studio, one, two, three, and penthouse apartments in a prime location in Dubai Marina
Since the Mobilization of construction works in Sep 2016, the project has involved a vast amount of raw materials and logistics. The raft foundation was completed in 48 hours, with a pour of over 420 cubic meters of concrete and 836 tons of reinforcement steel. With the full raft being cast, work is expected to quickly progress on the main floors, with the construction on track for a timely delivery.